1、鶴崗-大連高速公路小溝嶺(黑吉界)至撫松段ZT04標(biāo)(K581+000K610+000)級(jí)配碎石墊層試驗(yàn)段施工總結(jié)編制: 復(fù)核: 審核: xx路橋鶴大高速公路項(xiàng)目ZT04標(biāo)項(xiàng)目經(jīng)理部二一五年四月目錄第一章 試驗(yàn)段的工程概況1第二章 施工進(jìn)度周期及資源配置情況12.1進(jìn)度周期12.2資源配置12.3機(jī)械配置3第三章 施工準(zhǔn)備情況33.1技術(shù)準(zhǔn)備33.2材料準(zhǔn)備33.3施工水、電準(zhǔn)備43.4試驗(yàn)配合比準(zhǔn)備4第四章 級(jí)配碎石墊層施工44.1施工工藝44.2下承層準(zhǔn)備64.3施工測(cè)量放樣64.4混合料拌合74.5混合料運(yùn)輸74.6混合料攤鋪84.7碾壓9碾壓級(jí)配碎石9碾壓遍數(shù)確定9松鋪系數(shù)的確定94.
2、8邊緣修整144.9接縫處理144.10成品保護(hù)15第五章 試驗(yàn)段總結(jié)及質(zhì)量檢查結(jié)果155.1試驗(yàn)段總結(jié)165.2質(zhì)量檢查17第六章 施工過(guò)程中存在的問(wèn)題及整改措施17第七章 試驗(yàn)段結(jié)論17級(jí)配碎石墊層試驗(yàn)段施工總結(jié)路面墊層是在底基層下面鋪筑的承重層,本合同段采用級(jí)配碎石墊層結(jié)構(gòu)厚度潮濕段20cm,基巖段15cm。瀝青路面施工中,必須層層把關(guān),嚴(yán)格要求,在墊層施工中項(xiàng)目部給予高度重視,防止在墊層施工中出現(xiàn)原材料質(zhì)量不合格、配合比不準(zhǔn)確、拌和不均勻、碾壓不密實(shí)、接縫不平整等質(zhì)量弊病,以確保路面墊層的工程質(zhì)量。根據(jù)公路路面基層施工技術(shù)規(guī)范,為優(yōu)質(zhì)高效地完成墊層施工任務(wù),根據(jù)施工進(jìn)度計(jì)劃的要求,在駐
3、地辦、總監(jiān)辦的監(jiān)督和指導(dǎo)下,我合同段于2015年4月22日在K603+200-K603+500段右幅進(jìn)行了級(jí)配碎石墊層試驗(yàn)路段鋪筑。現(xiàn)將試驗(yàn)路段鋪筑情況總結(jié)報(bào)告如下:第一章 試驗(yàn)段的工程概況根據(jù)公路路面基層施工技術(shù)規(guī)范規(guī)定,為確保路面施工順利進(jìn)行避免盲目施工給工程帶來(lái)重大損失,根據(jù)本項(xiàng)目的實(shí)際情況及工程特點(diǎn),經(jīng)我項(xiàng)目經(jīng)理部多次現(xiàn)場(chǎng)考察,并仔細(xì)考慮,最終試驗(yàn)路段選在K603+200-K603+500,該段路面工程具有代表性,滿足試驗(yàn)段的施工要求,對(duì)全線的路面施工具有指導(dǎo)意義。級(jí)配碎石墊層試驗(yàn)段選于K603+200-K603+500右幅段落,全長(zhǎng)300米,該段墊層頂面寬度為13.195m,底面寬度
4、為13.495m,墊層設(shè)計(jì)厚度為0.20m。第二章 施工進(jìn)度周期及資源配置情況2.1進(jìn)度周期級(jí)配碎石墊層試驗(yàn)段施工開(kāi)始時(shí)間為:2015年4月22日,完成時(shí)間為2015年4月22日,工期為1天。2.2資源配置為優(yōu)質(zhì)高效地完成路面施工任務(wù),根據(jù)具體情況及施工特點(diǎn)的具體要求,我標(biāo)段抽調(diào)富有路面工程施工經(jīng)驗(yàn)的管理人員及業(yè)務(wù)骨干,組成精干高效的施工隊(duì)伍進(jìn)場(chǎng)。具體施工組織安排如下:項(xiàng)目管理人員一覽表表2.2-1序號(hào)職位姓名序號(hào)職位姓名1項(xiàng)目經(jīng)理雷云7安全部部長(zhǎng)王蘭貴2項(xiàng)目總工應(yīng)世明8物質(zhì)部部長(zhǎng)馬立新3生產(chǎn)副經(jīng)理趙凱雷9生產(chǎn)部部長(zhǎng)趙立國(guó)4工區(qū)主任馬曉兵 10技術(shù)主管王德猛5試驗(yàn)室主任吳小冬11技術(shù)員李寧6質(zhì)
5、檢部部長(zhǎng)于福瑞12技術(shù)員孫宏亮現(xiàn)場(chǎng)施工人員一覽表表2.2-2序號(hào)工種名稱數(shù)量(人)備注1技術(shù)人員32測(cè)量人員33試驗(yàn)員34工長(zhǎng)25普工106安全員27自卸車(chē)駕駛員108機(jī)械維修人員19電工210攤鋪機(jī)操作手211壓路機(jī)操作手312水車(chē)操作手12.3機(jī)械配置機(jī)械配置一覽表表2-3序號(hào)機(jī)械名稱規(guī)格型號(hào)功率、容量數(shù)量(臺(tái))1裝載機(jī)龍工953DZL5032水穩(wěn)攤鋪機(jī)ABG86209m13水穩(wěn)攤鋪機(jī)ABG882012m14振動(dòng)壓路機(jī)徐工223j23T25膠輪壓路機(jī)徐工XP30130T16水車(chē)東風(fēng)8T17運(yùn)輸車(chē)福田,豪沃23m10第三章 施工準(zhǔn)備情況3.1技術(shù)準(zhǔn)備2015年4月11日,由項(xiàng)目部技術(shù)負(fù)責(zé)人組
6、織相關(guān)技術(shù)人員對(duì)圖紙和本試驗(yàn)路段施工方案進(jìn)行討論,對(duì)技術(shù)人員及現(xiàn)場(chǎng)帶班工人進(jìn)行級(jí)配碎石墊層試驗(yàn)段工程的施工工藝、要點(diǎn)、質(zhì)量標(biāo)準(zhǔn)、試驗(yàn)檢測(cè)方法及頻率等進(jìn)行技術(shù)交底工作。圖3.1-1圖3.1-22015年4月21日,項(xiàng)目部路面技術(shù)負(fù)責(zé)人及安全員在現(xiàn)場(chǎng)對(duì)工人進(jìn)行技術(shù)交底和安全交底。圖3.1-2圖3.1-13.2材料準(zhǔn)備圖3.1-3級(jí)配碎石墊層原材料采用敦化市翰章鄉(xiāng)鴻瑞采石場(chǎng)生產(chǎn),碎石生產(chǎn)采用一次鄂是破碎后進(jìn)行。按公路工程集料試驗(yàn)規(guī)程JTG-2005進(jìn)行壓碎值、針片狀含量、篩分試驗(yàn),小于5(mm)顆粒含量進(jìn)行液限塑限試驗(yàn),所有檢測(cè)指標(biāo)均符合規(guī)范要求。3.2-1粗集料實(shí)驗(yàn)結(jié)果匯總表規(guī)格檢測(cè)指標(biāo)表觀密度(
7、g/cm3)針片狀(%)壓碎值(%)0.075顆粒含量(%)備注19-31.52.6785.4-1.49.5-192.6666.319.11.22.7009.0-1.13.2-2細(xì)集料實(shí)驗(yàn)匯總表規(guī)格檢測(cè)指標(biāo)表觀密度(g/cm3)液限(%)塑性指數(shù)0.075顆粒含量(%)備注0-4.752.6622013173.3施工水、電準(zhǔn)備水:為了確保合理的用水,我方根據(jù)施工需要,進(jìn)行了自打井。施工用電:進(jìn)駐工地以后,根據(jù)現(xiàn)場(chǎng)考察情況,生活區(qū)用電和施工用電利用地方供電系統(tǒng),架設(shè)施工電路,在紅石料場(chǎng)設(shè)1250KVA變壓器1臺(tái)(瀝青拌合站用水穩(wěn)定拌和站及生活用電所用),在翰章互通區(qū)料場(chǎng)設(shè)400KVA變壓器1臺(tái)(
8、水穩(wěn)定拌和站及生活用電所用),同時(shí),配備兩臺(tái)300KW發(fā)電機(jī)組,作為備用電源,以保證電網(wǎng)停電時(shí)能繼續(xù)施工。3.4試驗(yàn)配合比準(zhǔn)備按設(shè)計(jì)要求和公路土工試驗(yàn)規(guī)程(JTGE40-2007)要求,項(xiàng)目部試驗(yàn)室在規(guī)定的條件下,確定了級(jí)配碎石墊層配合比,并上報(bào)監(jiān)理工程師審核、驗(yàn)證。最終批復(fù)配合比為:墊層的配合比設(shè)計(jì)為:04.75mm:4.759.5mm:9.519mm:1931.5mm=25:25:12:38;最佳含水量為6.1%;最大干密度為2.22g/cm3。 第四章 級(jí)配碎石墊層施工4.1施工工藝圖4.1-1 碎石墊層施工工藝流程4.2下承層準(zhǔn)備圖4.2-2圖4.2-12015年4月21日對(duì)試鋪路段路
9、基彎沉、縱斷高程、橫坡度、寬度、平整度、壓實(shí)度、進(jìn)行了檢驗(yàn),各項(xiàng)指標(biāo)滿足規(guī)范及設(shè)計(jì)要求,并通過(guò)監(jiān)理工程師認(rèn)可,在級(jí)配碎石墊層施工前,進(jìn)行灑水復(fù)壓。4.3施工測(cè)量放樣圖4.3-2圖4.3-1級(jí)配碎石墊層試驗(yàn)段開(kāi)工前,測(cè)量人員根據(jù)設(shè)計(jì)施工圖中給定的逐樁坐標(biāo)、設(shè)計(jì)高程、設(shè)計(jì)寬度,及監(jiān)理工程師批復(fù)的導(dǎo)線點(diǎn)、水準(zhǔn)點(diǎn)(HD137,X=4790149.183,Y=508517.865,H=537.365;HD4-63,X=4790244.669,Y=508462.765,H=536.637) 圖4.3-1用全站儀按10m間距恢復(fù)路線中樁及邊樁,用白灰劃出墊層攤鋪設(shè)計(jì)寬度邊線;同時(shí)中樁位置向外側(cè)20cm及邊樁
10、位置向外側(cè)20cm處打鋼釬,這樣保證攤鋪的設(shè)計(jì)寬度,然后用水準(zhǔn)儀測(cè)量原地面控制點(diǎn)實(shí)際高程,再根據(jù)圖紙?jiān)O(shè)計(jì)高程和初擬松鋪系數(shù)(墊層經(jīng)驗(yàn)松鋪系數(shù)按1.25計(jì))計(jì)算出鋪筑高度,在固定鋼釬上作好控制標(biāo)高的標(biāo)記,并據(jù)此張拉鋼絲。中間導(dǎo)梁,采用拉線方法確定高度。圖4.3-2放樣后在每個(gè)斷面用50m鋼尺量出距設(shè)計(jì)線:1m、5.25m和11.5米處并采用鋼尺上作標(biāo)記進(jìn)行測(cè)量,在施工過(guò)程中,測(cè)量隊(duì)對(duì)相應(yīng)點(diǎn)高程作好詳細(xì)記錄,以此作為計(jì)算松鋪系數(shù)的測(cè)點(diǎn)。4.4混合料拌合圖4.4-1級(jí)配碎石墊層混合料采用1臺(tái)WDB600型拌和機(jī)集中拌和,在正式拌和混合料之前,拌和設(shè)備已調(diào)試完畢,自動(dòng)計(jì)量系統(tǒng)精度滿足設(shè)計(jì)要求,并經(jīng)過(guò)計(jì)
11、量單位標(biāo)定?;旌狭霞?jí)配組成和含水量達(dá)到規(guī)定要求。同時(shí)項(xiàng)目部安排專人對(duì)各料斗進(jìn)行檢查,料斗各出口不堵塞,做到了各種材料計(jì)量準(zhǔn)確。試驗(yàn)室配合拌和站操作人員進(jìn)行了級(jí)配和含水量檢測(cè),并根據(jù)原材料的含水量,計(jì)算出施工配合比,使混合料含水量達(dá)到滿足施工要求。4.5混合料運(yùn)輸拌合站距離試驗(yàn)段大約4公里,混合料的運(yùn)輸采用10臺(tái)后八輪雙橋自卸車(chē)運(yùn)至施工現(xiàn)場(chǎng),車(chē)況良好,裝料時(shí)車(chē)輛前后移動(dòng),拌成的混合料快速運(yùn)送到鋪筑現(xiàn)場(chǎng)。裝車(chē)時(shí),嚴(yán)格按“前、后、中”的順序裝料,用來(lái)減少混合料在下落過(guò)程中的重力離析。車(chē)輛運(yùn)輸時(shí)勻速行駛,從而減少運(yùn)輸途中的離析。運(yùn)料車(chē)在攤鋪試驗(yàn)段以外調(diào)頭,倒退駛?cè)霐備伂F(xiàn)場(chǎng)。料車(chē)到現(xiàn)場(chǎng)之后,實(shí)驗(yàn)人員先檢
12、查了料的外觀有無(wú)異常,并記錄料車(chē)到場(chǎng)時(shí)間,檢測(cè)合格后并且存料車(chē)不少于5輛時(shí),開(kāi)始攤鋪級(jí)配碎石,指揮人員組織料車(chē)倒料,倒料時(shí)指揮人員與攤鋪機(jī)手密切配合,使倒料與攤鋪之間保持連續(xù)作業(yè),沒(méi)有出現(xiàn)攤鋪機(jī)停機(jī)待料的情況。攤鋪過(guò)程中指揮人員隨時(shí)都在提醒駕駛員不能完全松開(kāi)剎車(chē),以免將料倒在地上,同時(shí)也不能踩死剎車(chē),以保證攤鋪機(jī)正常前進(jìn)。4.6混合料攤鋪圖4.6-1級(jí)配碎石墊層試驗(yàn)段K603+200K603+500右幅,全長(zhǎng)300米,該段墊層設(shè)計(jì)寬度為13.195m,兩臺(tái)攤鋪機(jī)組裝總寬為13.5m,其中ABG8820攤鋪機(jī)為7.5m,靠近分隔帶一側(cè),另一臺(tái)ABG8620攤鋪機(jī)為6m,靠近停車(chē)帶一側(cè)。攤鋪前灑水
13、車(chē)對(duì)下承層路基表面進(jìn)行灑水?,F(xiàn)場(chǎng)采用1臺(tái)ABG8620自動(dòng)伸縮式攤鋪機(jī)與1臺(tái)ABG8820攤鋪機(jī)進(jìn)行階梯式聯(lián)合攤鋪?zhàn)鳂I(yè),兩臺(tái)攤鋪機(jī)前后相距58m且相對(duì)距離保持穩(wěn)定。前臺(tái)攤鋪機(jī)采用了路側(cè)鋼絲和設(shè)置在路中的導(dǎo)梁控制高程,后臺(tái)攤攤機(jī)路側(cè)采用鋼絲、路中采用滑靴控制高程和厚度。前后兩臺(tái)攤鋪重疊250mm,中縫人工修整。圖4.6-2螺旋布料器中混合料高度沒(méi)過(guò)螺旋葉片,全長(zhǎng)一致,在攤鋪過(guò)程中螺旋布料器旋轉(zhuǎn)低速、勻速。運(yùn)輸車(chē)距攤鋪機(jī)料斗20cm左右停車(chē)。攤鋪機(jī)前頂靠住汽車(chē)后輪,然后起斗卸料,攤鋪機(jī)以1m/min進(jìn)行攤鋪,始終保持同路線方向行駛,攤鋪機(jī)行走時(shí)標(biāo)尺上自然垂落的左右測(cè)平傳感器的中心對(duì)準(zhǔn)級(jí)配碎石左右控
14、制邊線,用來(lái)保證攤鋪寬度、厚度準(zhǔn)確。攤鋪過(guò)程中有專人隨時(shí)注意材料離析情況,雙機(jī)聯(lián)結(jié)處容易離析,項(xiàng)目部設(shè)專人隨時(shí)消除粗細(xì)集料離析現(xiàn)象。墊層在開(kāi)始攤鋪5米長(zhǎng)時(shí),現(xiàn)場(chǎng)技術(shù)人員檢測(cè)攤鋪面的標(biāo)高及橫坡,合格后,再繼續(xù)攤鋪。攤鋪機(jī)每前進(jìn)10米,測(cè)量人員都檢測(cè)級(jí)配碎石攤鋪?lái)斆鏄?biāo)高,檢測(cè)位置同路基頂面檢測(cè)位置,記錄下數(shù)據(jù),根據(jù)之前測(cè)量的級(jí)配碎石底面標(biāo)高計(jì)算出級(jí)配碎石松鋪厚度及橫坡度。4.7碾壓4.7.1碾壓級(jí)配碎石混合料攤鋪、修整后,測(cè)量人員測(cè)量混合料松鋪表面高程,技術(shù)人員檢測(cè)橫坡度及平整度后,然后進(jìn)行碾壓,碾壓長(zhǎng)度以30m為一段落進(jìn)行碾壓作業(yè)。第一臺(tái)振動(dòng)壓路機(jī)由外側(cè)進(jìn)行碾壓,壓路機(jī)壓到路幅的1/3寬時(shí),第二
15、臺(tái)壓路機(jī)開(kāi)始碾壓。碾壓次序?yàn)椤跋鹊秃蟾?,先輕后重,先靜后動(dòng),先慢后快”,同時(shí)每遍的輪跡重疊1/2,并且碾壓壓路機(jī)后輪超過(guò)2段的接縫處,并且碾壓接頭不處在同一個(gè)斷面上,各部位碾壓次數(shù)始終保持相同。在碾壓過(guò)程中,壓路機(jī)沒(méi)有在在已完成的或正在碾壓的路段上“調(diào)頭”和急剎車(chē)。4.7.2碾壓遍數(shù)確定級(jí)配碎石墊層試驗(yàn)段的碾壓機(jī)械為自重為23t的徐工223j振動(dòng)壓路機(jī)和30t的徐工302膠輪壓路機(jī)。碾壓方法為第一遍以徐工223j振動(dòng)壓路機(jī)靜壓,碾壓速度1.52.0km/h;第二遍為徐工223j振動(dòng)壓路機(jī)低頻小振幅振壓,碾壓速度2.02.5km/h;第三遍、第四遍高頻大振幅碾壓完畢后壓檢測(cè)實(shí)度為94.7%;第五
16、遍采用了膠輪碾壓完畢后檢測(cè)壓實(shí)度為97.4%;第六遍膠輪碾壓完畢后檢測(cè)壓實(shí)度為98%;第七遍振動(dòng)壓路機(jī)靜壓收面。通過(guò)壓實(shí)度檢測(cè),確定級(jí)配碎石墊層的碾壓遍數(shù)為5遍,壓實(shí)度即滿足規(guī)范要求。4.7.3松鋪系數(shù)的確定觀測(cè)點(diǎn)樁號(hào):K603+200K603+500,共觀測(cè)28個(gè)斷面,每個(gè)橫斷面觀測(cè)4個(gè)觀測(cè)點(diǎn),共觀測(cè)112個(gè)點(diǎn),通過(guò)計(jì)算,級(jí)配碎石墊層松浦系數(shù)平均值為1.292。級(jí)配碎石墊層松鋪系數(shù)計(jì)算表樁號(hào)攤鋪前高程攤鋪后高程壓實(shí)后高程松鋪厚度壓實(shí)厚度松鋪系數(shù)K603+210右1m539.308右1m539.574右1m539.5050.2660.1971.3505.25m539.1975.25m539.4
17、85.25m539.4210.2830.2241.2639m539.0859m539.49m539.3390.3150.2541.24011.5m539.08711.5m539.35311.5m539.2860.2660.1991.337K603+220右1m539.432右1m539.662右1m539.6040.230.1721.3375.25m539.3385.25m539.595.25m539.5240.2520.1861.3559m539.2439m539.4949m539.4450.2510.2021.24311.5m539.19211.5m539.44611.5m539.3830
18、.2540.1911.330K603+230右1m539.5右1m539.75右1m539.6870.250.1871.3375.25m539.4425.25m539.6765.25m539.6220.2340.181.3009m539.3299m539.5959m539.5350.2660.2061.29111.5m539.26411.5m539.54311.5m539.4720.2790.2081.341K603+240右1m539.585右1m539.843右1m539.7870.2580.2021.2775.25m539.5185.25m539.7615.25m539.7130.243
19、0.1951.2469m539.4349m539.7139m539.6390.2790.2051.36111.5m539.37111.5m539.64411.5m539.5790.2730.2081.313K603+250右1m539.725右1m539.94右1m539.8850.2150.161.3445.25m539.6295.25m539.8565.25m539.8080.2270.1791.2689m539.5359m539.7759m539.7310.240.1961.22411.5m539.47411.5m539.71311.5m539.6680.2390.1941.232K60
20、3+260右1m539.817右1m540.028右1m539.9740.2110.1571.3445.25m539.7255.25m539.9485.25m539.8950.2230.171.3129m539.6339m539.8719m539.8160.2380.1831.301 11.5m539.56811.5m539.81511.5m539.7550.2470.1871.321 K603+270右1m539.899右1m540.102右1m540.0560.2030.1571.293 5.25m539.7775.25m540.045.25m539.970.2630.1931.363 9
21、m539.7179m539.9719m539.910.2540.1931.316 11.5m539.67911.5m539.9211.5m539.8550.2410.1761.369 K603+280右1m539.948右1m540.173右1m540.1440.2250.1961.148 5.25m539.8635.25m540.135.25m540.070.2670.2071.290 9m539.7839m540.0489m539.9990.2650.2161.227 11.5m539.75611.5m540.0111.5m539.9950.2540.2391.063 K603+290右1
22、m540.049右1m540.297右1m540.2590.2480.211.181 5.25m539.9685.25m540.2225.25m540.1660.2540.1981.283 9m539.8939m540.1489m540.0880.2550.1951.308 11.5m539.84611.5m540.09711.5m540.0290.2510.1831.372 K603+300右1m540.147右1m540.405右1m540.3410.2580.1941.330 5.25m540.0435.25m540.325.25m540.2550.2770.2121.307 9m539
23、.9959m540.2479m540.1950.2520.21.260 11.5m539.95811.5m540.19911.5m540.1450.2410.1871.289 K603+310右1m540.243右1m540.481右1m540.4280.2380.1851.286 5.25m540.135.25m540.3975.25m540.340.2670.211.271 9m540.0759m540.3249m540.2790.2490.2041.221 11.5m540.03511.5m540.28611.5m540.2390.2510.2041.230 K603+320右1m540
24、.328右1m540.584右1m540.5210.2560.1931.326 5.25m540.255.25m540.4965.25m540.4360.2460.1861.323 9m540.1889m540.4229m540.3650.2340.1771.322 11.5m540.14111.5m540.37711.5m540.3210.2360.181.311 K603+330右1m540.428右1m540.675右1m540.6090.2470.1811.365 5.25m540.3685.25m540.5995.25m540.5370.2310.1691.367 9m540.302
25、9m540.5319m540.4670.2290.1651.388 11.5m540.23311.5m540.48711.5m540.4220.2540.1891.344 K603+340右1m540.53右1m540.752右1m540.7010.2220.1711.298 5.25m540.4475.25m540.6625.25m540.6190.2150.1721.250 9m540.3869m540.5889m540.5450.2020.1591.270 11.5m540.34311.5m540.53811.5m540.5010.1950.1581.234 K603+350右1m540
26、.61右1m540.847右1m540.7860.2370.1761.347 5.25m540.5255.25m540.7535.25m540.7010.2280.1761.295 9m540.4679m540.6779m540.6270.210.161.312 11.5m540.43511.5m540.63211.5m540.5920.1970.1571.255 K603+360右1m540.701右1m540.951右1m540.8810.250.181.389 5.25m540.6055.25m540.8495.25m540.7970.2440.1921.271 9m540.5429m5
27、40.7799m540.7160.2370.1741.362 11.5m540.51111.5m540.72411.5m540.6820.2130.1711.246 K603+370右1m540.788右1m541.037右1m540.9750.2490.1871.332 5.25m540.7535.25m540.9515.25m540.910.1980.1571.261 9m540.6679m540.8789m540.8310.2110.1641.287 11.5m540.57211.5m540.82711.5m540.7790.2550.2071.232 K603+380右1m540.86
28、2右1m541.129右1m541.0670.2670.2051.302 5.25m540.8115.25m541.0395.25m540.9870.2280.1761.295 9m540.7569m540.9659m540.9240.2090.1681.244 11.5m540.71611.5m540.92211.5m540.8820.2060.1661.241 K603+390右1m540.972右1m541.22右1m541.160.2480.1881.319 5.25m540.8955.25m541.1215.25m541.0710.2260.1761.284 9m540.8339m5
29、41.0539m541.0070.220.1741.264 11.5m540.79111.5m541.01211.5m540.9670.2210.1761.256 K603+400右1m541.06右1m541.319右1m541.2590.2590.1991.302 5.25m540.985.25m541.2315.25m541.1750.2510.1951.287 9m540.9069m541.1499m541.0920.2430.1861.306 11.5m540.87811.5m541.11411.5m541.0670.2360.1891.249 K603+410右1m541.149右
30、1m541.406右1m541.3450.2570.1961.311 5.25m541.0775.25m541.3155.25m541.2580.2380.1811.315 9m541.0089m541.2419m541.1880.2330.181.294 11.5m540.97711.5m541.20411.5m541.1470.2270.171.335 K603+420右1m541.245右1m541.505右1m541.4410.260.1961.327 5.25m541.1865.25m541.4185.25m541.3650.2320.1791.296 9m541.0989m541.
31、349m541.2850.2420.1871.294 11.5m541.06111.5m541.29211.5m541.2470.2310.1861.242 K603+430右1m541.306右1m541.597右1m541.5270.2910.2211.317 5.25m541.2495.25m541.515.25m541.4460.2610.1971.325 9m541.1959m541.4379m541.3810.2420.1861.301 11.5m541.14211.5m541.38811.5m541.3350.2460.1931.275 K603+440右1m541.425右1m
32、541.68右1m541.6180.2550.1931.321 5.25m541.3545.25m541.5895.25m541.540.2350.1861.263 9m541.2739m541.5219m541.460.2480.1871.326 11.5m541.22111.5m541.47111.5m541.4120.250.1911.309 K603+450右1m541.54右1m541.77右1m541.7140.230.1741.322 5.25m541.4585.25m541.6895.25m541.6270.2310.1691.367 9m541.3699m541.6179m5
33、41.5650.2480.1961.265 11.5m541.32111.5m541.57211.5m541.5220.2510.2011.249 K603+460右1m541.604右1m541.862右1m541.7970.2580.1931.337 5.25m541.5225.25m541.7715.25m541.7110.2490.1891.317 9m541.4469m541.6999m541.6430.2530.1971.284 11.5m541.42211.5m541.65211.5m541.6040.230.1821.264 K603+470右1m541.692右1m541.9
34、37右1m541.8760.2450.1841.332 5.25m541.6395.25m541.8415.25m541.8030.2020.1641.232 9m541.5729m541.7759m541.7360.2030.1641.238 11.5m541.51311.5m541.73311.5m541.6920.220.1791.229 K603+480右1m541.761右1m542.016右1m541.9610.2550.21.275 5.25m541.6895.25m541.9255.25m541.8770.2360.1881.255 9m541.6369m541.8579m54
35、1.8190.2210.1831.208 11.5m541.56911.5m541.81111.5m541.7670.2420.1981.222 1.292 4.8邊緣修整碾壓結(jié)束后,邊緣人工修邊并且夯實(shí)。修邊時(shí)工人進(jìn)行拉線,然后進(jìn)行修整,修整后線形的平順,邊緣處沒(méi)有出現(xiàn)松散粒料。圖4.8-14.9接縫處理圖4.9-1試驗(yàn)段攤鋪結(jié)束,工人將攤鋪層末端收齊整平,然后碾壓,待終壓結(jié)束后先用三米直尺檢查,確定平整面與斜面的結(jié)合位置,在該位置挖槽并清除斜面部分。4.10成品保護(hù)圖4.10-1碾壓完成后的級(jí)配碎石墊層,為保證表面不受破壞,現(xiàn)場(chǎng)進(jìn)行封閉交通,并在路邊設(shè)置“施工重地,禁止通車(chē)”等標(biāo)志標(biāo)牌。第
36、五章 試驗(yàn)段總結(jié)及質(zhì)量檢查結(jié)果級(jí)配碎石墊層檢測(cè)項(xiàng)目及檢測(cè)方法級(jí)配碎石墊層實(shí)測(cè)結(jié)果序號(hào)檢測(cè)項(xiàng)目檢測(cè)點(diǎn)數(shù)合格點(diǎn)數(shù)合格率1壓實(shí)度(%)1212100%2平整度(mm)5050100%3高程(mm)302893%4寬度(mm)1010100%5橫坡(%)3030100%6厚度(mm)1212100%7彎沉值(0.001mm)3030100%5.1試驗(yàn)段總結(jié)通過(guò)該試驗(yàn)段的攤鋪,我們收集了以下指標(biāo):機(jī)械組合通過(guò)試驗(yàn)段的施工我們得出滿足施工的最佳機(jī)械組合為:WBD600拌和設(shè)備1套,ABG攤鋪機(jī)2臺(tái)(一臺(tái)ABG8620,另一臺(tái)ABG8820),徐工223j振動(dòng)壓路機(jī)2臺(tái),徐工XP301膠輪壓路機(jī)1臺(tái),灑水車(chē)1臺(tái),自卸車(chē)10輛,與施工方案一致,能夠滿足今后施工需要,根據(jù)運(yùn)輸距離增加運(yùn)輸車(chē)數(shù)量。碾壓方式徐工223j振動(dòng)壓路機(jī)靜壓1遍、小振1遍、強(qiáng)震2遍,徐工XP301膠輪壓路機(jī)碾壓1遍,即能滿足級(jí)配碎石壓實(shí)度及平整度要求
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 公司組織滑雪策劃方案
- 2025年物流與供應(yīng)鏈管理考試卷及答案
- 2025年現(xiàn)代文學(xué)與書(shū)法藝術(shù)考試試題及答案
- 2025年企業(yè)文化與內(nèi)部管理的考核試卷及答案
- 2025年品牌傳播與市場(chǎng)聯(lián)系考核考試試卷及答案
- 2025年可持續(xù)發(fā)展與環(huán)境政策基礎(chǔ)知識(shí)考試卷及答案
- 2025年媒體傳播與社會(huì)學(xué)習(xí)研究考試試卷及答案
- 2025年計(jì)算機(jī)網(wǎng)絡(luò)與信息安全課程考試題及答案
- 2025年材料科學(xué)與工程專業(yè)綜合能力測(cè)試卷及答案
- 2025年初中歷史學(xué)科教育考試試題及答案
- 工業(yè)管道工程工程量清單項(xiàng)目設(shè)置及計(jì)價(jià)
- 港口集團(tuán)績(jī)效考核方案
- 基于MATLAB的控制系統(tǒng)仿真及應(yīng)用-第5章-基于MATLABSimulink的控制系統(tǒng)建模與仿真課件
- 一二次深度融合成套柱上斷路器匯報(bào)課件
- 解凍記錄表(標(biāo)準(zhǔn)模版)
- 初中數(shù)學(xué)北師大八年級(jí)下冊(cè)(2023年修訂) 因式分解岷陽(yáng)王冬雪提公因式法教學(xué)設(shè)計(jì)
- 金屬非金屬礦山安全規(guī)程
- 生活飲用水游離余氯方法驗(yàn)證報(bào)告
- DB32∕T 186-2015 建筑消防設(shè)施檢測(cè)技術(shù)規(guī)程
- C-TPAT反恐知識(shí)培訓(xùn)ppt課件
- 巡檢培訓(xùn)課件.ppt
評(píng)論
0/150
提交評(píng)論